News & Updates

Project Overview

Delta Sands LLC is developing a 3-million-ton-per-year wet-plant near Buffalo, Texas.

Development Timeline

Phase

Description

Status

Q4 2025

Permitting & design

Completed

Q1 2026

Clearing, utilities, site development

In Progress

Q2 2026

Wet plant and loadout construction 

In Progress

Q3 2026

Full commercial operations — 3 MMTPY nameplate.

Upcoming

Community & Economic Impact

Construction and full-time roles, contractor opportunities, and expanded local tax base in Leon & Freestone Counties.

Market Context

With Comstock, Aethon, Mitsui E&P USA, Expand Energy, Hilcorp Energy advancing Western Haynesville programs, regional demand for high-quality, local proppant is accelerating. Our plant offers shorter hauls, and consistent 40/200 supply.